Director Robin Sporn Invited to Westminster

Friday, February 2nd, 2018

Robin was personally invited to Westminster last week to meet with Government officials along with the Federation of Master Builders to discuss the current economic problems facing the construction industry. Robin raised a number of pertinent concerns the affect of which on future policies we shall wait and see. Robin commented ” I felt honoured to be invited to the meeting and indeed the fact that the government appear to be beginning to recognise the importance of SME’s within the construction industry must spark a glint of hope that due respect and consideration may be awarded to our sector moving forward. Policies are often driven by the needs of the “Top 10″ civil construction companies, this needs to change. ”

 

Hazel House Construction Progress

Friday, February 2nd, 2018

Construction continues.1st fix M&E underway along with lower ground floor tanking system. Specialist minimal windows to the rear extension have been measured and are on order.

Progress 31Jan18 (3)

Progress 31Jan18 (4)

Progress 31Jan18 (8)

 

Oak House Construction Progress

Friday, February 2nd, 2018

Construction continues on program. Tanking system to the lower ground floor installed along with underfloor heating pipework and screed to this area. Roof covering is underway and external masonry repairs nearing completion. 1st fix M&E is due to start next week.Progress 31Jan18 (12)Progress 31Jan18 (16)

Progress 31Jan18 (5)

Chestnut House Construction Progress

Friday, February 2nd, 2018

Construction continues on program. Windows are currently being installed and roof coverings started. Second Considerate Constructors visit undertaken and passed with flying colours

 